Third Terminal Set for Partial Launch on December 16

Photo: Collected

Staff Correspondent:

DHAKA, Nov 29 (BDReports24) — The third terminal of Hazrat Shahjalal International Airport will begin partial operations with four flights on December 16, with the Civil Aviation Authority of Bangladesh set to sign a 15-year concession agreement with a Japanese consortium on Monday to operate and maintain it.

CAAB Chairman Air Vice Marshal Md Mostafa Mahmud Siddiq disclosed the details at a press conference at the authority’s headquarters in Dhaka on Sunday, saying the agreement followed lengthy negotiations, technical and financial analyses and the completion of legal procedures.

The terminal’s concession area will be handed over to the operator within 15 days of signing. The operator must handle at least 25 percent of regular international flights within eight months of the handover, and all scheduled international passenger and cargo operations will gradually shift to the new facilities within 14 months.

The agreement sets strict service standards. The first bag must reach the conveyor belt within 15 minutes of an aircraft landing, while the last must arrive within 42.5 minutes for narrow-body aircraft and 47.5 minutes for wide-body aircraft. Average check-in queue times are set at 5-10 minutes for business-class passengers and 20-30 minutes for economy passengers, with repeated failures drawing financial penalties of $5,000 to $35,000.

Spread over 230,000 square metres, the terminal has an annual capacity of 2.4 crore passengers, with 127 check-in counters, 129 passport control counters and 16 baggage conveyor belts. Its new cargo terminals have a combined annual handling capacity of 820,411 tonnes, quadrupling the airport’s cargo-handling capacity. Once fully operational, the existing two terminals will be used for domestic, Hajj and other non-scheduled flights.