Staff Correspondent:
DHAKA, Nov 27 (BDReports24) — The gas fire at Inani in Cox’s Bazar has been brought under control after burning for 31 consecutive days, as the drilling team of Bangladesh Petroleum Exploration and Production Company Limited (Bapex) completed the final operation on Friday.
In the final operation, the Bapex team extinguished the fire within 10 minutes, assisted by three Fire Service units that had sprayed water from 9:00 am to reduce the heat around the well. A casing pipe was inserted 13 feet into the well, immediately putting out the flames.
Gas is still leaking from the well, and a drilling pipe and chemical cementing will be needed to stop it fully — work Bapex estimates will take another four to five days, said SM Nafefun Arham, head of the Bapex geological survey team. Bapex also plans to collect gas samples from the well.
The fire broke out on 27 October after gas emerged from a 1,000-foot-deep tube well in Inani. Bapex monitored the situation for the first 15 days, after which another team worked for the following 14 days to bring the fire under control.