visible, said Executive Engineer Dewan Md Abdul Quader of the Padma Multipurpose Bridge Authority.
“The rest two 40 and 41 spans will be installed within December 15,” he added.
Meanwhile, a floating crane Tian-E brought the span from the construction ya...
Much awaited Padma Bridge only 300 meters away
With the installation of 39th span today, only 300 meters will remain in hand to complete a 6,150-meter or 6.15 kilometers long much awaited Padma multipurpose Bridge.
The span was installed over the pillars no. 10 and 11 at Munshganj’s Maowa point making 5,850 meters of the bridge’s main structure
visible, said Executive Engineer Dewan Md Abdul Quader of the Padma Multipurpose Bridge Authority.
“The rest two 40 and 41 spans will be installed within December 15,” he added.
Meanwhile, a floating crane Tian-E brought the span from the construction ya...
visible, said Executive Engineer Dewan Md Abdul Quader of the Padma Multipurpose Bridge Authority.
“The rest two 40 and 41 spans will be installed within December 15,” he added.
Meanwhile, a floating crane Tian-E brought the span from the construction ya...